This post was contributed by a community member. The views expressed here are the author's own.

Schools

Coultrap Building Will Come Down June 3

Fences are up, and the Coultrap building is set for demolition sooner than expected—on June 3.

Geneva School Board President Mark Grosso mentioned in passing Tuesday night that the Coultrap building would be demolished on June 3.

Previous mentions were that the building would be demolished sometime in July so that work could be completed prior to the start of the 2013-14 school year, but fencing already has gone up around the building and preparations put in place for the demolition.

School District 304 Director of Facility Operations Scott Ney said after the meeting that the timing of the building demolition would be named later and that the "wrecking ball" image is a little out of date.

"There's not a wrecking ball. There's actually a claw that will be demolishing that building," he said. "I don't know an exact time. We'll be having our meeting tomorrow, and we'll be issuing something after that."

School District 304 will pay Alpine Demolition $545,900 to do the work and another $140,200 for asbestos abatement at the school.The board also determined that it would rename—or "rededicate" the Fourth Street central office as the "Coultrap Educational Services Center" in memory of Harry Coultrap, the educator that played such an important role in the development of Geneva schools and its "tradition of excellence."

Holian Industries submitted the low big for the aesbestos removal. 

We’ve removed the ability to reply as we work to make improvements. Learn more here

The views expressed in this post are the author's own. Want to post on Patch?